News Flash Home
The original item was published from 7/29/2019 3:57:06 PM to 1/1/2020 12:00:07 AM.

News Flash

Construction Updates for New Development

Posted on: July 29, 2019

[ARCHIVED] The Brunswick Update 7/29

As we near completion of the erection of the precast portion of the parking deck, we will be resuming work on the storm line that runs down Holcomb Bridge and across Buford Highway as well as foundation work for Building 1000. We have reached the point where we will need to extend the fence to the curb, close the sidewalk within our project site, and demo the existing sidewalk. These areas are highlighted below. We plan to move the fence the first part of next week, and we will provide “Sidewalk Closed Ahead” signs at both ends of the project site.



Facebook Twitter Email