Construction Updates for New Development

Posted on: July 14, 2020

[ARCHIVED] N. Peachtree Sidewalk Update 7/14/20

Our City Engineer held a short conference call/webinar with residents at 12-noon today to give a high-level update on the project and answer questions. The city was informed this morning by Gwinnett DWR and the contractor that they have pushed the planned water outage  to Thursday 7/16. This date seems firm, because all testing is complete. Gwinnett DWR will confirm the outage to any affected properties. We are hopeful for some real visible progress in the 2-3 weeks ahead. There will be continued traffic disruption, as the next phase involves installation of storm pipe in one travel lane.