The following are the lane closures associated with Jimmy Carter this week, December 16, 2013 - December 20, 2013 from 9am - 4pm, M - F:
*****Tuesday, December 17, 2013 - Jimmy Carter EB; 1 Left Lane b/w Crescent Dr & I-85 SB On Ramp; Jimmy Carter WB; 1 Left Lane b/w Oakbrook Pkwy & Goshen Springs
*****Wednesday, December 18, 2013 - Jimmy Carter EB; 1 Left Lane b/w Crescent Dr & I-85 SB On Ramp Jimmy Carter WB, 1 Left Lane b/w Oakbrook Pkwy & Goshen Springs
******Thursday, December 19, 2013 - Jimmy Carter EB, 1 Left Lane b/w Crescent Dr & I-85 SB On Ramp Jimmy Carter WB, 1 Left Lane b/w Oakbrook Pkwy & Goshen Springs
The contractor (ER Snell) will be boring along the Bridge median for the future Ped Poles/Underground Traffic Signal
******Dates are contingent on whether ER Snell can complete necessary work on Tuesday, December 17th