Public Safety Building

PSBRendering

Project Overview

The City is building a brand-new Public Safety Building that will be home to both the Police Department and Municipal Court! It’s going up on the site of the former Norcross Library, right at the corner of Buford Highway and Stevens Road. We’ve got a powerhouse team bringing this project to life: CROFT & Associates designed the building, Turner & Townsend Heery/AEI is managing the project, and Reeves Young is leading the construction. Big things are happening—stay tuned!

Construction Phase

The Construction phase is when the groundwork—literally—begins! From site prep and laying the foundation to seeing real progress rise up, this is where big plans turn into exciting reality. We’ll be sharing weekly updates filled with photos and videos so you can follow along every step of the way. Check out our overview schedule below—or click on a date to explore photo updates and see the progress for yourself!

Overview Schedule


  • July 14, 2025 – Construction officially begins

  • September 2025 – Grading and utility work completed

  • October 2025 – Concrete slab poured and completed

  • March 2026 – Roofing work completed

  • June 2026 – Interior work, parking lot, and landscaping completed

  • July 2026 – Final touch-ups and punch list items completed

  • August 11, 2026 – Target completion date

  • August-September 2026 – Move-in begins